Building Committee Meeting September 17, 2024

The Building Committee met on September 17, 2024. The main concern of the committee is the projected cost of construction for the current proposed plan. Several financial options were discussed. We are awaiting the completion of revised civil engineering drawings which will dictate appropriate clubhouse and pool locations on the yacht club’s property.
It was decided to enlist the assistance of several commercial contractual firms who have expressed interest in the project and have offered to generate very preliminary cost estimates for the most recent set of design plans.
The committee also gave the chairman the authority to contact several commercial pool contractors in order to get an estimated cost for a pool. The committee consensus being that the pool would be constructed first to minimize pool downtime for the club members.